Project → Modules. A module is a named outcome with tasks in it. Unlike a cycle, it is not a window of time you fill — it is a thing that is either finished or not, and it may take three cycles or half of one.

Milestone, epic, initiative, release. Same idea.

  • The work has a shape somebody outside the team asks about: is Payments v2 done?
  • The work spans cycles, so a cycle cannot answer for it.
  • You want a progress number for an outcome rather than for a fortnight.

If every task in the project is in exactly one module and the modules are called January, February, March — those are cycles. If the modules are called Frontend, Backend, Infra — those are labels. A module that nobody would describe as finished is not a milestone, and it will quietly turn into a second, worse backlog.

Progress Done over total, in tasks and in points
A filter module = "Payments v2" anywhere, including in a saved view
A row on the timeline Its tasks drawn together, with its own bar
A row on the portfolio roadmap Which is where a module earns its keep — see across projects

A task can be in a cycle and a module at once, and that is the normal case. Sprint 14 says when somebody is doing it; Payments v2 says what it is part of. Filtering on one does not disturb the other, and the two progress numbers answer two different questions that people routinely confuse:

  • The cycle number is are we going to finish what we said we would this fortnight.
  • The module number is are we going to finish this thing at all.

A cycle at 90% and a module at 20% is a completely normal and completely healthy Tuesday.